
The 232nd Engineer
Combat Company, an
integral part of the 442nd Regimental
Combat Team (RCT), was activated on
February 7, 1943 at Camp Shelby, Mississippi,
and is the only company in the United
States Army whose entire officer and
enlisted personnel is composed of
Americans of Japanese ancestry. Unlike
other companies of combat engineer
battalions, this unique organization
operated in training as a separate
unit without being under the direct
supervision of a combat engineer battalion
or infantry regiment’s S-1,
S-2, S-3, and S-4.
The company occupied
hutments on the crest of a hill overlooking
the 442nd Infantry Regiment to the
west and the 522nd Field Artillery
Battalion to the east. Under its special
table of organization authorized by
the War Department, the company was
authorized one hundred ninety four
enlisted men and five officers, but
operated with an overstrength of the
ten enlisted men and two officers.
Every individual was issue arms under
its table of equipment and was trained
to use them. Its mobile equipment
consisted of fifteen 2-½ ton
trucks, four ¼ ton trucks,
four motorcycles, one ¾ ton
command and reconnaissance car, one
compressor, one bulldozer, one prime
mover, four 1-ton cargo trailers,
one 8-ton trailer, and three 3-½
ton pole-type trailers.
During basic training,
which commenced on May 10, 1943, the
men were trained to do the work necessary
for combat engineers, in addition
to training for physical fitness and
military discipline. Learning by doing
demolition work, building trestle-bend
bridges, assembling and disassembling
portable steel truss bridges, building
pontoon and infantry foot-bridges,
crossing streams in assault boats,
laying mine-fields and barbed wire
barricades, were some of the duties
of the combat engineers. Physical
fitness tests were passed with honors
at the close of basic training.
Soon after passing
basic training tests, unit training
was begun. At this stage of training,
the men spent more of their time out
in the field putting to practical
use the knowledge acquired during
basic training than being trained
in garrison. Spending days in the
field building bridges, doing actual
demolition work, constructing roads,
going on nine and twenty-five miles
forced marches were part of weekly
schedules.
The real test of the
efficiently of the 232nd Engineers
came during the D-Series maneuvers
when the 442nd Infantry Regiment together
with the 69th Infantry Division conducted
mock battles in the woods of Mississippi.
Preparing demolition for bridges and
road craters, making road reconnaissance,
building bridges, building and maintaining
roads, laying mine-fields, setting
up water points and engineer dumps,
and even going in line as infantry
were some of the work done by the
engineers with such efficiency as
to win the admiration and praise of
umpires and fellow troops.
Orders for the preparation
for overseas movement came on March
23, 1944, and like other units of
the 442nd Combat Team, feverish preparation
began immediately under the supervision
of the 24th Headquarters, Special
Troops, and 2nd Army. Show-down inspections
after show-down inspections were conducted
to see that the men were properly
equipped with clothing, arms, and
field equipment, and to see that all
organizational equipment were fit
for combat. Old records were crated
and put in storage, and organizational
equipment were wrapped, sealed, crated,
and properly labeled to be shipped
over-seas with the personnel. Everyone
was kept busy at all times. In the
midst of all these activities the
tables of organization and equipment
were changed four times to add to
the confusion and excitement. Equipment
that was formerly authorized had to
be de-crated and turned in to quartermaster
and engineer dumps, and records had
to be revised to meet the requirements
of new tables or organization and
equipment. Over-strength personnel
were transferred to other organizations
one day and recalled on the following
day. The personnel section was kept
busy making class E and F allotments,
so that the men could have their money
sent home conveniently.
After the final inspection
was over, the unit boarded trains
enroute to Camp Patrick Henry, Virginia
on April 23, 1944. In Camp Patrick
Henry, more showdown inspections were
conducted to insure that every soldier’s
equipment was complete and serviceable
for combat. For the first time instructions
were given on complete censorship
of mail and other forms of communications.
“E”
Day and Convoy
Arrival and Training in Italy
At 1230 hours on May
1, 1944, the 232nd Engineer Combat
Company entrained at Camp Patrick
Henry, Virginia for Hampton Road,
Port of Embarkation, Newport News,
Virginia to begin the final phase
of the journey on ships bound for
an unknown destination. Upon arrival
at this port of embarkation, the unit
was immediately ordered to board the
liberty ship, Thomas Cresap. Accommodations
on board ship were shared with the
206 Army Ground Forces Band and a
platoon of signal corpsmen. Amidst
the bustle of learning new terms used
by the ship's crew to describe the
various parts of the ship, preparations
for the journey began, crews for lifeboats
and life rafts were assigned, and
security instructions were given.
Each enlisted man was assigned bunks
in hold Number 2, and officers were
assigned cabins in hold Number 3.
The journey across
the Atlantic began at 0200 hours on
May 3, 1944. As the convoy moved out
to sea, and the last signs of the
shoreline began to disappear from
sight, many were the hearts that were
pensive and sad to leave behind the
land they loved. The ship's rail and
deck were crowded with men until the
land dropped beyond the rim of the
horizon. When the convoy hit the deep
turbulent waters of the rough Atlantic,
the men turned to card playing, reading,
checkers, chess, and the ever present
dice games to pass the time away.
There were quite a few men who were
unfortunate enough to be forced to
stay in their bunks to fight off seasickness.
The hardy ones were put to work scrubbing
the deck, going on K-P, guard, and
general clean-up details. On the third
day out at sea, the ship's PX opened
for business, and the men were supplied
with ample candy, toilet articles,
and miscellaneous articles. At least
once a week the 206 Army Band entertained
the men by playing a few pieces on
deck, if the weather was favorable,
and in the hold daring inclement weather.
One of the chief sources
of conversation was the speculation
as to the probable destination of
the convoy, but when the convoy filed
through the strait of Gibraltar and
entered the calm waters of the Mediterranean
Sea, all doubts were cleared away
as to the ship's final destination.
On the ship one of
the most popular songs sung among
the men was "A Trip on a Liberty
Ship" which was written and composed
on board ship by Corporal Daniel D.
Betsui of Hanapepe, Kauai, Hawaii.
The song was introduced as part of
the entertainment for the men in hold
number 2.
The ship dropped anchor
in Augusta Bay, Sicily at 0200 hours
on May 26, 1944, and in that interlude,
boxing contests were held among the
Army personnel and men of the ship's
crew. Judo exhibitions were subsequently
given by some of the men of the 232nd
Engineers.
After being on board
ship for 23 consecutive days the convoy
finally entered Naples harbor, and
there the unit saw wide-scale destruction
of harbor facilities, buildings, and
ships. These reminders of the grim
tasks lying ahead of the men sobered
some of the exhilarations of setting
foot on land again. The dock to which
the Thomas Cresap heaved to was a
partially demolished luxury liner,
which had been converted into a pier
to accommodate ships temporarily.
The unit debarked at 1800 hours and
marched through the shambles of bombed
and partially demolished Naples to
Stazione Garibaldi, and entrained
for staging area number 4·
in the vicinity of Bagnoli. In the
orchard of the staging area the unit
got over their sea legs amidst the
dust and discomforts of a crowded
bivouac area, and began receiving
organizational equipment for combat.
A small percentage of the men were
allowed to go on passes to visit the
city of Naples and Bagnoli. The men
were paid for the first time in Europe
in this area.
When the unit was
finally fully equipped, it embarked
from Bagnoli for Anzio on a LST on
June 6, 1944. More signs of war's
havoc were seen, as the men marched
through the deserted streets of Anzio
to their bivouac area 8 miles out
of the town. From their now bivouac
area, the men were transported to
the Fifth Army Bathing and Clothing
Exchange where they experienced their
first 5 minutes showers and full exchange
of clothing.
On the motor convoy
from Anzio to Civitavecchia from June
9 to June 10, 1944, the company was
temporarily lost in the historic city
of Rome at 0130 hours on June 10.
The convoy finally resumed its course
after roaming aimlessly in the city
when Route number I was found, and
arrived at Civitavecchia at 0830 hours.
At Civitavecchia the unit was attached
to 109th Engineer Combat Battalion
of the 34-th infantry Division, veteran
of the African and Italian campaigns.
From Civitavecchia
the company moved up the vicinity
of Tarquinia on June 11, 1944, join
the line companies of the 109th Engineers
- The day after the company arrived,
the 109th Engineers gave instructions
on German and Italian mines, and demonstrations
were given on the removal of mines
in an active German mine-field. On
the 15th of June 1944 Staff Sergeant
Ernest Kagawa and 16 enlisted men
conducted a mine school for the 442nd
Infantry Regiment. A small percentage
of men were given one-day passes to
Rome in this area.
On the 21st of June
1944, the company left Tarquinia by
motor convoy to Grosetto. There the
water purification unit with Sergeant
Tokio Okamura in charge was established
for the first time in Italy. More
classes on mines and minefields were
conducted. Mutual respect and lasting
friendships were developed here amongst
the two organizations as the men got
acquainted by working together and
participating in baseball and volleyball
games. The next stepping off place
to the front for the 232nd Engineers
was Caldana, and from there on to
C. Vetricella. On the convoy to C-Vetricella,
the company suffered its first casualties
when a squad truck wont off the road
and overturned.
The
Italian Campaign
The 26th of June will
be long remembered by the men of the
232nd Engineer Combat Company as the
first day in line as combat engineers.
Not knowing what to expect, the men
were naturally apprehensive and tense
as the motor convoy with its heavy
engineer equipment rolled into its
first bivouac area only 300 yards
behind the front lines in the vicinity
of Suvereto, Italy. The unit received
its baptism of enemy fire on this
convoy when an 88 mm shell landed
near a squad truck and wounded four
men. Before the motors of the squad
trucks had time to cool off in the
bivouac area, the company received
its first orders to sweep the roads
leading to Suvereto for mines in direct
support of the 4422nd Infantry Regiment.
Upon receipt of orders
from the 109th Engineer Combat Battalion,
the 232nd Engineers relinquished their
support of the 4s-G2nd Infantry after
three days of action, and subsequently
gave direct support to the 168 Infantry
and to the 133 Infantry respectively.
Although the German
retreat up the Italian peninsula was
rapid, the rugged Italian terrain
with its numerous hills and vales
provided excellent opportunities for
demolitions by the Germans to retard
the Allies. Bridges after bridges
were blown up, and numerous minefields
were laid at road junctions, and on
grounds that could possibly be used
for bypasses, and on vital supply
routes. The unit was kept busy day
and night, working by platoons on
12 hours shifts. The company bivouac
area seldom stayed in one area for
over a week and was always within
range of enemy artillery. In their
conscientious and meticulous work
in minesweeping and reconnaissance
the men often went far into the front
lines, and frequently became involved
in skirmishes with enemy patrols.
On 6 July 1944, a reconnaissance patrol
from the first platoon consisting
of three men encountered small arms
fire from a nest of enemy snipers.
Because of the overwhelming strength
of the enemy, the rest of the platoon
was immediately summoned to the scene
and deployed in an enveloping movement.
In the ensuing firefight eight Germans
were killed and four captured as prisoners.
In this action the company lost its
only fatal combat casualty in the
entire Italian campaign.
The D-7 and R-4 bulldozers
were used constantly to carve out
bypasses, fill road and shell craters,
and to remove wrecked enemy tanks,
vehicles, and carcasses of dead animals
off the roads.
During the rapid advance
up the Italian boot, the company averaged
at least one by-pass a day in order
to keep the supply line open to front
line troops. On the 13th of July 1944
in the vicinity of Pomaja, Italy,
the first platoon of 232nd Engineers
had to build three by-passes in order
to keep up with the 'advancing infantry.
Sites for the bypasses were selected,
cleared of mines, and then marked
off with tracing tapes so that the
bulldozer could work. While the dozer
worked, some of the men were put on
guard as security against snipers,
and the remainder of the men worked
on the by-passes by clearing shrubs,
laying culverts, and other work.
After over a month
of duty in line the company was relieved
on 28 July 1944 in the vicinity of
Tripalle, Italy, and pulled back to
the vicinity of Collemezzano, Italy,
for its first rest period.
On the l6th of August
194·4· the company was
relieved from attachment to the 109th
Engineer Combat Battalion and attached
to the 442nd Regimental Combat Team,
and further attached to the 310th
Engineer Combat Battalion of the 85th
Infantry Division. The company was
relieved from attachment to the 310th
Engineer Combat Battalion on 18 August
1944 and attached to the 313th Engineer
Combat Battalion of the 88th Infantry
Division in the vicinity of Castelfiorentino,
Italy.
For the defense of
the Arno River sector in the vicinity
of Florence, Italy, the unit was put
on infantry reserve for the 442d Infantry
Regiment when the company entered
its bivouac area in Scandicci, Italy
on 21 August 1944. For the first time
the men were used to accompany infantry
patrols as engineers to neutralize
booby-traps across the Arno River
into enemy territory. On 2 September
1944 the second platoon of 232nd Engineers
was attached to the 760th Tank Battalion
to serve as infantry support in the
88th Infantry Division attack across
the Arno River.
Throughout the Rome-Arno
campaign which took them from Suvereto
to Pisa from 26 June to 28 July 1944,
and to the Arno River near Florence
from 21 August to 7 September 1944,
the Engineers supported the attack
by building, repairing, and maintaining
supply and evacuation routes, neutralizing
mine-fields and booby-traps, and selecting
and building fording sites across
the Arno River. On 5 September, in
the vicinity of Signano, Italy, at
two fording sites across the Arno,
the company removed 97 Tellermines
and 12 "S" mines from two
large minefields which extended into
water 2 1/2 to 3 feet deep and which
necessitated probing with bayonets
and using mine-detectors in waist-deep
water. Some of the Tellermines were
booby-trapped with 3 kilograms of
explosives to make removal more difficult
and dangerous. After the crossing
was made, scores of schu-mines and
booby-traps were removed on the north
slope of the Arno River.
In the process of
supporting infantry units, the 232nd
Engineer Combat Company built 26 bypasses,
six culverts, ten fills, four bridges
including a foot bridge and a Brockway
steel tread way bridge; removed approximately
24 booby-traps and over 300 anti-tank
mines from mine-fields, road shoulders,
road junctions and river fords; captured
20 prisoners; and removed over a ton
of prepared demolition charges from
five bridges the Germans failed to
blow up.
The unit was relieved
from attachment to the 88th Infantry
Division and moved to the vicinity
of Castiglioncello on 6 September
1944. On 10 September 1944 the company
boarded the Liberty Ship, John Holms,
at Piombino, Italy, together with
the 100th Battalion and the Cannon
Company for Naples. Organizational
and part of individual equipment were
loaded on company trucks that were
driven down to Naples in a motor convoy
via Rome.
The unit debarked
in Naples at 1030 12 September 1944
and entrucked for the Nevada Area
outside of Naples. Here preparations
for the trip to France were begun,
lost individual and organizational
equipment were replaced and the men
were kept physically fit by following
a training schedule. On 21 September
1944, the unit left the Nevada Area
for Staging Area N-4 in the vicinity
of Bagnoli, Italy, and at 0700 26
September 1944 the unit left the staging
area for Naples and embarked on the
USS Samuel Chase at 0800 for southern
France.
The
French Campaign
On 29 September 1944,
the 232nd Engineer Combat Company
debarked at Marseilles, France and
was transported to the C.B.S. staging
area near the city of Septemes, France.
During the nine days the company was
staged in this area, strong wind,
rain, and nearly freezing weather
made life uncomfortable for the men
as preparations were made for the
trip to Charmois, France. Also during
this period, a training schedule of
four hours daily was put into effect.
The journey to Charmois, France, a
distance of about 450 miles, was begun
by motor convoy at 0700 9 October
1944. As the convoy moved northward,
the weather became steadily colder,
and the men huddled closer together
on topless squad trucks to keep warm.
Over-night stopovers were made in
the vicinities of Vienne and Vesoul.
At 1030 11 October 1944 the unit arrived
in the vicinity of La Buffo, France
whore the company was attached to
the 111th Engineer Combat Battalion
of the 36th Infantry Division.
At dusk on 14 October
1944 the company left the vicinity
of La Buffo, France by motor convoy
for its assembly area in the vicinity
of Fontenay, France. A tank dozer
with five enlisted men from 6617 Engineer
Mine Clearing Company was attached
to the company at 1800 on the same
day.
The second platoon
of the 232nd Engineers pulled out
of the company bivouac area in direct
support of the 442nd Infantry at 0800
15 October 1944. At 1000 hours a mine-sweeping
crow of the second platoon encountered
a heavily booby-trapped abatis road
block over a quarter of a mile long
on the only supply and evacuation
route for the 442nd Infantry about
one mile west of Bruyeres, France.
Attempts to clear the abatis were
delayed when a heavy crossfire from
four enemy machine guns opened up
on the working crows. Work was resumed
by the first platoon at 0800 16 October
after the infantry moved up and cleared
out snipers and wiped out the four
machine gun nests covering the abatis,
periodic intense mortar and artillery
barrages from enemy guns that were
zeroed in on the abatis hampered work,
but in spite of the barrages, the
platoon kept doggedly at the job because
the route had to be opened in order
to evacuate the wounded and to take
supplies to the advancing infantry.
When the work was begun, gasoline
engine driven chain saws were used,
but they were abandoned in favor of
two men hand saws when the noise of
the gasoline engines attracted enemy
artillery and mortar barrages. The
debris and logs were pushed off the
road by the tank-dozer operated by
five men from the 6617 Engineer Mine
Clearing Company. The road was opened
for traffic at 1630 after eight and
a half hours of pains-taking work.
In the process of clearing the abatis
numerous booby-traps and anti-tank
mines were removed and heavy casualties
were inflicted on the company.
During the intense
fighting in rugged terrain and under
adverse weather conditions in eastern
France from 14 October to 18 November
1944, the 232nd Engineer's duties
assumed greater proportions because
of the numerous booby-trapped abatis
road blocks and poor roads rendered
muddy and slippery by constant rain
which hampered the 4aG2d RCT's operations
in the dark woods of the Vogues mountains.
The Engineers underwent intense mortar
and artillery barrages, engaged enemy
snipers, machine gun nests, and hostile
patrols while supporting the 442nd
Infantry. They cleared the booby-trapped
abatis and anti-tank and anti-personnel
mines in spite of the "zeroed
in" barrages of the enemy. When
muddy, impassable roads between Belmont
and Biffontaine which were vital for
supply, evacuation, and armor traffic,
presented a problem, the Engineers
solved it by laying over a mile of
plank-board and corduroy roadways
and by dumping truckloads of gravel
on the road after mud, water, and
debris were removed with the aid of
a bull-dozer and hand tools. This
road was constantly repaired and 'maintained
by the Engineers to prevent enemy
shelling and rainy weather from making
the road impassable.
In addition to the
normal activities of the engineer
unit, the 232nd Engineer Combat Company
was called upon to give close support
to some of the more spectacular operations
of the 442nd Regimental Combat Team.
On 27 October to 30 October 1944,
the Engineers, attached to the 4·42d
Infantry, participated in the daring
rescue of the isolated 1st Battalion,
141st infantry Regiment, “the
lost battalion of World War II",
from German encirclement in a heavily
wooded ridge in Forat Domaniale Du
Champ, about 3 kilometers due east
of Biffontaine, eastern France. Two
platoons of the 232nd Engineers played
an unheralded but vital part in this
action. Accompanying the front-line
infantrymen as service troops, the
Engineers were subjected to the hazards
of small arms and automatic fire,
artillery and mortar barrages, booby-traps,
skillfully manned road blocks, as
well as the cold and wet weather and
rugged mountain and heavily forested
terrain. During the four-day period,
the Engineers enhanced the success
of the operations by sweeping roads
and abatis for mines under heavy enemy
fire, removing over 30 "S"
and "R" mines in the path
of the advancing infantry. To facilitate
the supply and evacuation, the unit
maintained the muddy roads, laying
stretches of plank roads and removing
mud and hauling gravel, clearing numerous
abatis blocking the way of the advancing
troops and supply trains, and building
culverts across badly shelled roads,
despite heavy enemy barrages made
more dangerous by tree bursts and
the danger of infiltrating and counter-attacking
enemy troops. In the vicinity of Biffontaine,
when another Engineer unit refused
to clear a minefield blocking the
advance of the 442nd infantry because
of the heavy enemy fire, the 232nd
Engineers went ahead and cleared the
field for their comrades, winning
the admiration and gratitude of the
riflemen. Four large shelters were
also constructed for the 442nd CP
to protect it from tree bursts and
from the extreme cold and rain.
On 5 November 1G·
when the infantry was in dire need
of reinforcements, the company was
relieved from attachment to the 111th
Engineer Combat Battalion and attached
to the 442nd Infantry by vocal order
of the Commanding General, 36th infantry
Division, and ordered to be in line
as infantry by 0600 6 November 1944.
At 0430 6 November the first platoon
relieved A Company, 100th Battalion,
442nd infantry in a defensive sector
in the vicinity of Biffontaine, France.
The platoon kept active contact patrols
with C Company, 100th Battalion, 442nd
Infantry on its left flank, and the
143rd Infantry on its right flank,
until it was relieved at 0800 8 November
1944 by F Company, 442nd Infantry.
During the Vogues
campaign, the company neutralized
over a hundred “R” mines,
scores of “S” mines and
booby-traps, cleared hundreds of yards
of abatis roadblocks, and built two
bypasses.
At 1400 17 November
19144· the company left Bruyeres,
France for Chenimenil, France where
preparations for motor movement to
Nice, France was begun. The long trip
to Nice was begun at 0713 19 November
1944. Over-night stopovers were made
in the vicinities of Dijon and Valence.
The company arrived at St. Jeanne,
France at 1930 21 November 1944.
From St. Jeanne five
percent of the personnel were allowed
to go on pass to Nice daily, and the
champagne campaign of southern France
was launched. At 0700 23 November
the second platoon was attached to
the Third Battalion, 442nd Infantry
at Sospel, France. At 1530 24 November
1944 the company departed from the
vicinity of St. Jeanne for its billet
area at Rue Ballet, Nice. On 27 November
1944 the third platoon was attached
to the 100th Battalion, 442nd Infantry
at Menton, France.
During the Engineer's
tour of duty in the southern sector
of the French Maritime Alps sector
from 23 November 1944 to 17 March
1945, reconnaissance patrols surveyed
all roads from Menton to Sospel and
effected a defensive plan that skillfully
utilized anti-personnel minefields
and barbed-wire entanglements.
The 232nd Engineers
operated with personnel attached to
various elements of the 442nd Infantry.
On I January 1945, elements of E and
H Companies, 2d Battalion, 442nd Infantry,
holding a fort on Mt. Grosse were
faced by enemy troops located in another
fort about 1000 yards away in the
valley. Because of a steep incline,
the American troops were unable to
cover the forward slopes, and the
enemy was able to infiltrate to the
fort under the protection of the defile.
The Engineers were called upon to
mine this "blind spot" to
prevent infiltration. Disregarding
mortar fire and booby traps laid by
the enemy, the Engineers worked under
cover of darkness in de-activating
booby-trapped grenades rigged up by
the Germans and laid 33 anti-personnel
mines on the frozen forward slopes
150 yards down and extended a single-strand
protective barbed wire along the friendly
side of the minefield. Two men were
wounded when a booby-trap was set
off in the dark, but the Engineers
succeeded in their mission.
From 1 December 1944
to 16 March 1945 the company strung
up over 10,000 yards of barbed-wire
entanglements, laid over 50 trip-flares
and over 4,200 anti-personnel mines
in 99 minefields, and filled thousands
of sand bags for infantry barricades.
The company built a H-15 trestle-bent
bridge at Sospel and another at Menton,
one grease rack for the 3rd Battalion,
442nd Infantry, and a 14 mule capacity
mule shed in the vicinity of Menton.
Familiarization mine and demolition
schools were conducted for the j22d
Field Artillery Battalion and the
442nd Infantry. On 19 December 1944
men from the first platoon pulled
a one man German submarine from the
sea in the vicinity of Menton.
The versatility of
the 232nd Engineers as a service unit
was demonstrated in an ingenious shower
unit they voluntarily built for the
comfort and morale of the 442nd RCT.
The shower unit was assembled with
makeshift parts, which were skillfully
reconverted or adapted, into an efficient
unit. Originally the shower unit was
powered with a French truck motor,
but after extensive repairs were made,
the French truck engine was replaced
with an American ½-ton jeep
engine that supplied power to run
a German electric dynamo capable of
producing 380 volts of electricity.
The trailer was originally part of
a mobile German electric power plant
and its wheels came from salvaged
American GMC 2½ ton trucks.
The hot water tank formerly served
as a condenser of a beer factory,
the electric blower came from the
ventilating system of a French fort
in the Maritime Alps, the fuel pump
motor was adapted from an Italian
diesel self-propelled Jun, and the
fuel control valve was evolved from
a French acetylene welding torch.
Swiss thermometers control water temperature,
while showerheads and water hoses
were acquired from a demolished resort
hotel and a water purification unit.
From this conglomeration of makeshift
materials acquired at odd time, the
Engineers built a shower unit that
is capable of producing approximately
50 gallons of hot water per minute.
Through the initiative, ingenuity,
and ability of the Engineers, the
LG42cl RCT has been blessed with its
own electronically run shower unit
since the French Maritime Alps campaign.
This extra service rendered by the
Engineers has made it possible for
the 442nd RC ' front line men to have
a shower unit set up in close proximity
of their area in every campaign or
in every theater and has helped materially
in the morale of the regiment.
On 16 March 1945 the
company was received by French troops
and pulled back to the 4-42d Combat
Team assembly area at Antibes, Franco.
The company departed from Antibes,
France by motor convoy to the D.B.S.
staging area 10 miles northeast of
Marseilles, France on 18 March 1945.
Here at the staging area all excess
equipment and all mobile equipment
and clothing were turned in and final
showdown inspections and preparations
for embarkation movement were made.
On 23 March 1945 the company left
Marseilles, on the LST 907 on a convoy
to Livorno, Italy.
Appenines
and Po Valley Campaigns
After an uneventful
trip from Marseilles, France, the
Company debarked at Livorno, Italy
at 1200 23 March 19~5 and departed
from the port area for the P.B.S.
staging area in the vicinity of Pisa,
Italy, in this area the company was
relieved from assignment to D.B.S.
and assigned to the Fifth Army and
re-equipped with new vehicles and
engineer equipment. For combat operations,
the company was attached to the 9~d
Infantry Division,
On 29 March the 232nd
Engineers arrived at its new bivouac
area five miles northwest of Lucca,
Italy where a command inspection by
Brigadier General Woods and Aide of
the 92d Division was made of clothing,
equipment, personnel, and arms on
3 April 1945. At 2100 on the same
day the unit left the bivouac area
and moved into the assembly area of
the 4·Li·2d RCT in a
valley one and a half miles southeast
of Pietrasante, Italy.
When the 442nd infantry
launched its attack on 5 April 1945,
the third platoon of the Engineers
was called upon to support the infantry
by sweeping roads for mines and maintaining
them in the area north of Mount Altissimo.
During the rapid advance
of the 4·42d Infantry the dozer
was used constantly to fill road craters,
remove carcasses of dead animals from
supply lines, and build bypasses.
On 10 April 1945, the 100th and 2d
Battalions advancing north and east
of Massa in a drive toward Carrara,
Italy, were in nee~ of a suitable
supply and evacuation route. The road
from Massa to Canevara had been made
impassable by a 30-yard long crater
dug by the retreating Germans on the
outskirts of Massa. It was also mined
with anti-tank, anti-personnel, and
artillery shells converted into mines
with pressure devices that were buried
too deep for detection by electrical
mine detectors or probing.
The 232nd Engineers
began the work of opening this vital
route at 1300 hours 10 April 1945
in spite of heavy enemy artillery
barrages that intermittently hit the
area and mines that were highly sensitized
by the long period underground. The
company, realizing the critical need
for the road for evacuation and supply,
worked continuously, alternating among
the three platoons of 40 men each
on every shift, under intermittent
barrages that caused some damage to
equipment and wounded two riflemen
standing in the work area. By methodical
hand probing and by the use of detectors
when feasible, 20 12" artillery
shells rigged as mines were removed
with truck winches. In addition, 30
schu-mines, 3 Tellermines, and 5 Italian
box-mines were removed.
The highly sensitized
nature of the mines and the difficulty
of detection made the work of the
dozer operators a hazardous proposition.
Four dozer operators who braved this
danger in order to help open the route
without delay were wounded when undetected
mines blew up their dozers. Despite
the fact that 1 officer, 4 dozen operators,
and 2 other enlisted men were injured
in four mine explosions and shelling
continued unabatingly, the work was
continued without let-up.
Beehive charges were
utilized in blowing up the side of
the cut to get material for an embankment.
When one of the wrecked D-7 dozers
could not be removed, an ingenious
solution was evolved whereby the immovable
dozer was used as a trestle and a
30-feet bridge of 10-ton capacity
was built over it. After working from
1300 10 April, the Engineers had the
supply and evacuation route open by
2200 hours the next day. The opening
of this vital link from Massa to Canevara
with a minimum of delay helped open
the only supply route and alleviated
the serious supply difficulty caused
by terrain that precluded the use
of hand-carry parties.
Frequently details
of men from the company were detached
and attached to 442nd Infantry units
to clear gaps through mine-fields
and do other engineer work during
infantry assaults. During the attack
of Mount Belvedere by the 2c Battalion,
one squad of the first platoon was
attached to F Company to do engineer
work from 7 April to 10 April. On
12 April three enlisted men were attached
to I Company, and four enlisted men
were attached to L Company. One squad
of the first platoon was attached
to the 2d Battalion from 13 April
to 15 April, and from 20 April to
23 April one squad of third platoon
was attached to the 100th Battalion
to do engineer work.
On 15 April the 232nd
Engineer Combat Company was ordered
to cease all engineer work and to
be in line as infantry in the vicinity
of Gragnana, Italy. The first platoon
relieved I Company, 442nd Infantry
on hill 574, and the second and third
platoons relieved K Company on hills
580 and 539 respectively. The platoons
were under constant artillery and
small arms fire, but they kept contact
with each and with the forward CP
with the aid of telephones and by
means of contact patrols. On 17 April
the company was relieved as infantry
and resumed regular engineer work.
Between 5 April and
23 April the Engineers removed over
20 Tellermines, 4 stock mines, 23
“R” mines, 57 schu-mines,
47 M2A1 anti-personnel American mines,
5 Italian box mines, 20 12”
artillery shells improvised as anti-tank
mines, 1 plastic mine, over 100 pounds
of cratering charges; demolished 15
mortar duds and 1 rocket bomb; filled
over 25 road craters; built 12 by-passes
with culverts, I expedient assault
boat infantry support bridge over
100 feet long, 2 trestle-bent bridges,
and 2 ford crossings; removed 100
stalled vehicles in the vicinity of
Ferrada, Italy; and built miles of
mule trails on hills and mountains
impassable to vehicles.
After the collapse
of the German Armies in Italy, the
company was kept busy doing extensive
road and bridge reconnaissance from
Tendola, Italy to Monaco along the
Ligurian coast, and from Geneva to
Alessandria, and repaired damaged
bridges and roads.
On 16 May the 232nd
engineers moved into the 442nd RCT’s
bivouac area in the vicinity of Ghedi,
Italy and began working in the Fifth
Army Enemy Concentration Area. The
company took over all engineer work
in the area when the 169th Engineer
Combat Battalion was relieved on 24
May 1945. Among the work the company
had to take over were a carpenter
shop, a paint shop, two shower units,
and one water point in addition to
clearing debris, stringing barbed
wire barricades around the prisoner
of war enclosures and supervising
the work of the prisoners.
Source: Internet
Written by:
T/5 George Goto
232nd Engr.(C) Co
Unit Historian |